Rachel Tennant Rachel Tennant

Insulation and wallboard installation nearing completion

Outside the Nereda basins, the 36" exterior process pipe connections are being finalized. Inside the Operations & Maintenance building, insulation and wallboard installation is nearing completion, creating the foundation for a fully functional operations hub.

Read More
Guest Contributor Guest Contributor

Crews installing HVAC ductwork

Inside the main electrical and O&M buildings, crews are installing HVAC ductwork and applying ceiling coatings. At the headworks, final connections are being made to the 42-inch influent line.

Read More
Guest Contributor Guest Contributor

Rare look inside the sludge holding tank

The AquaDisk filters have arrived on-site, these will polish the effluent after biological treatment and prepare it for final disinfection. We also get a rare look inside the sludge holding tank, which will never look this spotless again.

Read More
Guest Contributor Guest Contributor

Veneer blockwork on office side nearly finished

This week, we’re seeing exciting developments at the operation and maintenance building, where veneer blockwork on the office side is nearly finished. Interior framing and rough-in work are also wrapping up.

Read More
Guest Contributor Guest Contributor

Structural and utility enhancements across the site

This week, construction efforts have focused on structural and utility enhancements across the site. At the headworks structure, crews are nearing completion of the final grit chamber wall pours, bringing this area closer to its finished form.

Read More
Guest Contributor Guest Contributor

Framing and final plumbing nearing completion

This week, the O&M building reached a major visual milestone with the installation of colored veneer block, giving the exterior a cohesive and durable finish that matches the maintenance bay walls.

Read More
Guest Contributor Guest Contributor

HVAC and plumbing now installed!

This week we can see some new progress inside the O&M building, as crews are working to frame out the walls, HVAC, and plumbing of the second floor offices and control room.

Read More
Guest Contributor Guest Contributor

Updates on critical infrastructure installments

Notable developments are underway on the Main Electrical Building, which will house the plant’s high-voltage switchgear and motor drives, along with a dedicated generator room for the relocated 3MW generator from the IWRF.

Read More
Guest Contributor Guest Contributor

Crews putting final touches on masonry walls

This week, the pace hasn’t slowed. Aerial shots reveal the evolving landscape around the Main Electrical and Blower Buildings, where crews are putting the final touches on masonry walls—setting the stage for the upcoming roof and slab work.

Read More
Guest Contributor Guest Contributor

O&M building being prepped for concrete roof pour

This week, crews are tackling multiple tasks at once. The O&M building is being prepped for its concrete roof pour, while masonry walls are being waterproofed in anticipation of the colored veneer block installation.

Read More
Rachel Tennant Rachel Tennant

O&M building’s roof sheet fully installed

The O&M building’s roof sheeting is now fully installed, setting the stage for foam insulation and a concrete layer to be poured in the coming weeks. This marks a big step in enclosing the structure, allowing work on the interior to advance.

Read More

Thank you to the Florida Department of Environmental Protection for your generous support granted toward this project. Disclaimer: This work is funded in part through a grant agreement from the Florida Department of Environmental Protection’s Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.