Guest Contributor Guest Contributor

Crews installing HVAC ductwork

Inside the main electrical and O&M buildings, crews are installing HVAC ductwork and applying ceiling coatings. At the headworks, final connections are being made to the 42-inch influent line.

Read More
Guest Contributor Guest Contributor

Rare look inside the sludge holding tank

The AquaDisk filters have arrived on-site, these will polish the effluent after biological treatment and prepare it for final disinfection. We also get a rare look inside the sludge holding tank, which will never look this spotless again.

Read More
Guest Contributor Guest Contributor

Veneer blockwork on office side nearly finished

This week, we’re seeing exciting developments at the operation and maintenance building, where veneer blockwork on the office side is nearly finished. Interior framing and rough-in work are also wrapping up.

Read More
Guest Contributor Guest Contributor

Structural and utility enhancements across the site

This week, construction efforts have focused on structural and utility enhancements across the site. At the headworks structure, crews are nearing completion of the final grit chamber wall pours, bringing this area closer to its finished form.

Read More
Guest Contributor Guest Contributor

Framing and final plumbing nearing completion

This week, the O&M building reached a major visual milestone with the installation of colored veneer block, giving the exterior a cohesive and durable finish that matches the maintenance bay walls.

Read More
Guest Contributor Guest Contributor

HVAC and plumbing now installed!

This week we can see some new progress inside the O&M building, as crews are working to frame out the walls, HVAC, and plumbing of the second floor offices and control room.

Read More
Guest Contributor Guest Contributor

Updates on critical infrastructure installments

Notable developments are underway on the Main Electrical Building, which will house the plant’s high-voltage switchgear and motor drives, along with a dedicated generator room for the relocated 3MW generator from the IWRF.

Read More
Guest Contributor Guest Contributor

Crews putting final touches on masonry walls

This week, the pace hasn’t slowed. Aerial shots reveal the evolving landscape around the Main Electrical and Blower Buildings, where crews are putting the final touches on masonry walls—setting the stage for the upcoming roof and slab work.

Read More
Guest Contributor Guest Contributor

O&M building being prepped for concrete roof pour

This week, crews are tackling multiple tasks at once. The O&M building is being prepped for its concrete roof pour, while masonry walls are being waterproofed in anticipation of the colored veneer block installation.

Read More
Rachel Tennant Rachel Tennant

Chlorine contact chamber reaching its final wall pour

 This week, exciting developments are taking shape. At the Nereda basins, crews are making significant progress on the pipe support structure, a crucial step in delivering process air and electronic control to each reactor.

Read More
Guest Contributor Guest Contributor

Kicking off the new year with continued progress

Last week, on the final Wastewater Wednesday of 2024, we reflected on the significant progress of the FPUA sewer treatment plant on Energy Lane. Despite weather challenges and minor delays, construction is on schedule and within budget, with 50% of the work completed and most structures finished.

Read More
Guest Contributor Guest Contributor

Wrapping up a productive 2024!

On the first day of 2025, a Wastewater Wednesday, we are full of gratitude and joy for the progress and updates that the last year has brought for the new FPUA sewer treatment plant being built on Energy Lane.

Read More

Thank you to the Florida Department of Environmental Protection for your generous support of $15 million granted toward this project. Disclaimer: This work is funded in part through a grant agreement from the Florida Department of Environmental Protection’s Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.