Crews completing final landscaping details
An updated aerial view of the WRF highlights how far the facility has come as it moves closer to full completion.
Work beginning on the Moore’s Creek Booster Pump Station
On the conveyance side, work is beginning on the Moore’s Creek Booster Pump Station, which will play a key role in moving wastewater toward the new Mainland Water Reclamation Facility.
Crems completing additional electrical and cabling work across Nereda basins
This week, crews are completing additional electrical and cabling work across the Nereda basins. This work connects key treatment components, including the sludge thickeners and water level correction tanks, to the electrical building.
Final site restoration and finishing work continues
This week, final site restoration and finishing work continues across the WRRF property. Crews are actively installing sod and operating irrigation systems in common area.
Visible progress continues with the final stages of civil sitework
This week, visible progress continues with the final stages of civil sitework. Crews are re-grading disturbed areas and installing sod and hydroseed in common spaces to restore the site and promote proper drainage and stabilization.
Crews focus on testing and tuning systems
This week, work continues at the Water Reclamation and Reuse Facility as crews focus on testing and tuning systems in preparation for startup.
FPUA welcomes FDEP representative for on-site visit
As construction progresses, we were pleased to welcome a representative from the Florida Department of Environmental Protection for an on-site tour of the work underway.
Ribbon Cutting Highlights
We are grateful to the partners, elected officials, FPUA staff, and community members who joined us to celebrate this moment. Their support and teamwork helped make this project and this day possible.
Project moves deeper into final stages
Following last week’s ribbon cutting, the project continues to move forward on multiple fronts. The event marked an important milestone, bringing together community leaders, project partners, and more than 200 attendees to tour the facility and recognize the collective effort behind this program.
FPUA Hosts Ribbon-Cutting for Mainland WRF
On January 9, 2025, Fort Pierce Utilities Authority welcomed more than 200 guests to the ribbon cutting of the Mainland Water Reclamation and Reuse Facility, marking a major milestone in the community’s long-term wastewater program.
Crews laying down curbs and landscaping
This week we can see new progress at the O&M building, as crews are laying down the curbs and landscaping for the final push.
Pipe crews advancing work on plant lift stations
Crews are laying asphalt at the O&M building’s parking lot, a milestone that sets the foundation for the loop road construction scheduled to begin in the coming weeks.
Still time to submit artwork for the 2026 Commemorative Calendar!
There is still time to submit artwork for the 2026 Commemorative Calendar, which will celebrate the completion of Phase 1 of the wastewater treatment plant relocation. We’re looking for pieces that reflect clean water, environmental care, and Fort Pierce’s sustainable future.
Clean Water Inspiring Creativity
This week, we’re inviting the community to help us tell that story through the Fort Pierce Art Competition, a chance to showcase how clean water, technology, and environmental stewardship are shaping Fort Pierce’s future. Local artists, students, and community members of all ages are welcome to participate.
Crews installing new force main in downtown Fort Pierce
In Downtown Fort Pierce, crews are installing a new force main which will ultimately serve as one of the main force mains to the new sewer treatment plant on Energy Lane. This week, roads remain closed between Indian River Drive and 2nd Street, at the intersection of 2nd Street and AE Backus Avenue, and on Avenue B just west of US 1.
Construction on the site continues to deliver measurable results
This week construction activity on the plant site continues to deliver measurable results. Final interior finishing is wrapping up inside the Operations and Maintenance building, setting the foundation for daily field coordination once the facility goes live.
Cabinetry and painting are nearly complete!
Inside the Operations and Maintenance Building, interior work is progressing steadily. Cabinetry and painting are nearly complete, creating a finished environment that will soon support furniture delivery and installation.
Continued mechanical progress and detailed finishing throughout the site
This week’s work highlights continued mechanical progress and detailed finishing throughout the site. At the Nereda basins, crews are installing process air piping along its elevated route between the blower building and treatment basins.
Conduit Cable Systems Installed
At the Nereda basins, crews are installing the conduit cable tray system, which will connect and organize the on-tank equipment to support future electrical and control components.
FPUA recognized as a 2025 Utility of the Future Today in Water Reuse
Fort Pierce Utilities Authority is proud to be recognized as a 2025 Utility of the Future Today in Water Reuse.
This national recognition from the Water Environment Federation (WEF) honors utilities that lead with innovation, sustainability, and community service. Since the program began, 241 utilities have received this distinction, including 41 recognized in 2025.
Thank you to the Florida Department of Environmental Protection for your generous support granted toward this project. Disclaimer: This work is funded in part through a grant agreement from the Florida Department of Environmental Protection’s Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.